Project Description
The job covers preperation of shop and as-built drawings, material suppy, installation, testing, commissioning and start-up of the below listed works at mentioned areas. In the scope, 800km halogenfree small power and lighting and 73km feeder cables, 135 tonnes cable trays, 50km EMT conduit and accessories, 112 ea floor and 140 ea shop panelboards, 5500 ea lighting fixtures, 4500 ea sockets have been used.
· All electrical and AV works in 3 floors of board members and CEO, ballroom floor, auditorium for 800 people, branch bank, library and speciality dining floors, and other special decoration areas
· Network and UPS socket and wiring in typical office floors of Tower 1
· Floor and shop panels, complete with central billing system in Towers 2 and 3
· Main feeder cabling and cableways for these feeders.